Hitek Consultants Ltd were commissioned by Quest Interiors to provide Building Services design and site management for two Nuffield Hospital, Design and Build projects with respect to clean rooms & operation complexes.

At Woking Hospital the two existing operating theatres and sterile wash room were taken out of commission for a period of 6 weeks during which time the two theatres were refurbished and new wash room equipment was installed which also involved the creation of new sterile stores, autoclave areas, sterile washers and a TSSU.

At Tunbridge Wells Hospital a new two storey extension containing a third theatre and bedroom wing were provided, together with a full refurbishment of two operating theatres and re-planning of recovery and sterile wash room facilities. Within the 34 week contract duration the hospital would allow only 19 days without two of the three operating theatres being operational and hence a previously timed programme of seven phases was required to achieve this. Two of the theatres were provided with Howorth ultra clean ventilation canopies.

Mechanical Engineering Services included new air conditioning & ventilation, automatic controls, hot & cold water services, heating and medical gases, steam and above ground drainage. Electrical Services included new lighting & emergency lighting, main distribution board relocation, small power and standby power, data, fire alarms & nurse call systems.

Nuffield Hospitals
Nuffield Hospitals
Nuffield Hospitals